Saturday, June 28, 2014

Information Systems - sample exam paper June 2014

Section A – All seven questions in [A] are compulsory and must be attempted (60%)

Two case studies are provided for analysis:
Case 1 – ABC Ltd.
ABC Ltd is a large pharmaceutical company. It has a proactive attitude toward new technologies. It began exploring the potential of the Internet in 1993. Managers soon realized that, by using intranets, they could reduce many of the problems associated with developing applications on a wide variety of hardware platforms and network configurations. Because the benefits were so obvious, the regular financial justification process was waived for intranet application development projects. The Information Systems group that helps user departments develop and maintain intranet applications increased its staff from 3 to 10 employees in 15 months
Case 2 – XYZ Ltd.
XYZ Ltd., an advertising agency, has offices in various parts of the country. The company discovered that, in developing presentations for bids on new accounts, employees found it helpful to use materials from other employees’ presentations on similar projects. Unfortunately, it was very difficult to locate and then transfer relevant material in different locations and different formats. After doing research on alternatives, the company identified intranet technology as the best potential solution.
XYZ Ltd. hired ACAS Consulting Firm to help develop the system. It started with one office in 2006 as a pilot site. Now the company has a sophisticated corporate-wide intranet and extranet in place. XYZ Ltd. did not do a detailed financial analysis before starting the project. David Li, the  Chief Information Officer, explained, “The system will start paying for itself the first time an employee wins a new account because he had easy access to a co-worker’s information.”
[Question A]
Required:
Based on the cases of ABC Ltd. and XYZ Ltd, answer the following questions:
1)      Briefly describe the following terms:
a.       Intranet
b.      Extranet
(6 marks)
2)      Briefly describe one method of financial analysis for IT project evaluation
(4 marks)
3)      Briefly explain the main advantage(s) of implementing an IT project with a pilot site
(6 marks)
4)      Briefly describe the following components in the benefits-dependency network of Peppard, Ward and Daniel, using examples from the ABC Ltd and XYZ Ltd cases:
a.       IT Enablers                              (4 marks)
b.      Enabling changes                   (4 marks)
c.       Business Changes                  (4 marks)
d.      Benefits                                    (4 marks)
e.       Investment objectives           (4 marks)

5)      Under what circumstances is the “invest first, analyze later” approach appropriate? And under what circumstances is the approach inappropriate?
(8 marks)
6)      How long do you think the “invest first, analyze later” approach will be appropriate for intranet projects in the cases of ABC Ltd and XZ Ltd.? When (and why) should the emphasis shift to traditional project justification approaches for ABC Ltd. and XYZ Ltd.?
(8 marks)
7)      What are the risks of going into projects that have not received a thorough financial analysis in the cases of ABC Ltd. and XYZ Ltd.? How can ABC Ltd and XYZ Ltd. reduce these risks?
(8 marks)

Section B – Answer any two of the following three questions (40%)

[Question B1]
The increased popularity of ‘lightweight’ project methods, for example Agile, has led to some people questioning the need for well established structured methods. There is no method that is always best: each is more appropriate in certain circumstances.

1)      To what kind of project is an Agile approach most suited?
(4 marks)
2)      List 3 benefits of prototyping
(6 marks)
3)      What 3 essential things do you need to run a Joint Application Development (JAD) workshop?
(6 marks)
4)      What is meant by the expression ‘time-boxing’?
(4 marks)

[Question B2]
Your company has decided that it needs a new stock control system and that an off-the shelf package is the best solution. The main tasks have been identified and duration assessed as follows:

A
Draw up a functional requirements specification
4 weeks
B
Consider various relevant software packages and select one
3 weeks
C
Identify and specify the necessary hardware and communications equipment
2 weeks
D
Order the hardware and equipment
1 week
E
Identify the key package modifications needed to meet the functionality required
2 weeks
F
Modify the software package as necessary
8 weeks
G
Accept delivery and install all hardware and equipment needed for the package
10 weeks
H
Design a training plan
2 weeks
I
Set up a testing plan
3 weeks
J
Unit test all the amended package modules
3 weeks
K
Train the users
2 weeks
L
Full  integration and acceptance testing
3 weeks
M
Implement the new system
1 week

B cannot start until A is completed
C, E, H and I cannot start until B is completed
D cannot start until C is completed
F cannot start until E is completed
G cannot start until D is completed
J cannot start until F, G and I are completed
K cannot start until H is completed
L cannot start until J and K are completed
M cannot start until L is completed

1)      Draw an activity-on-node diagram for these 13 project tasks (A to M). Calculate and display on the diagram, with a node layout key, the earliest and latest start and finish times and float of each task.
(10 marks)
2)      Describe how each of the following changes to task duration (on their own) would affect the  critical path and project duration:
a.       Task A – reduced to 3 weeks
b.      Task E – increased to 5 weeks
(4 marks)
3)      List and explain briefly 3 advantages and 3 disadvantages of using an activity-on-node diagram for a project plan in comparison with using a Gantt chart.
(6 marks)

[Question B3]
You are an IT manager within a software house. You have been asked to draw up a plan to provide security within the system you are developing. Describe what measures you can take to ensure:
1)      The reliability and integrity of your data
2)      Physical security
(8  marks)
Write brief notes on the following:
3)      IT Outsourcing
4)      Business  process re-engineering
5)      IT governance
6)      Usability in software design
(12 marks)





-          End -

No comments:

Post a Comment